TUESDAY--Classroom:
7:45 to
8:00A Registration - Text Material
8:00 to 12:00 P Current Standards--A92.2-2001
Old Standards
International Standards
Truck Design
a. Types and location of insulating systems
b. Lower current metering system
c. Corona rings, gradient control system and shields
purpose and application
Test procedures and variables which affect results
a. A.C. testing
b. D.C. testing
Test procedures for basket liners
Discussion of shield and capacitance compensation method
Current monitoring for bare hand hot line work
Test Programs--problems
found and solutions
12:00 to
12:45 P Lunch (Furnished)
1:00 to 5:00 P Demonstration and instruction in use of equipment
Demonstration of current metering systems
Test of aerial lift with high voltage D.C.
Flashover demonstration and corona effect
Demonstration of Wet Test
Test of hydraulic hose
Test of leveling rod
Test of
fiberglass section
WEDNESDAY--Field:
7:45 to
8:15 A Drive to field site--transportation furnished
8:15 to 11:45 A Testing of aerial lifts - demonstration
and hands-on instruction
Test on basket liner discussion of results
Presentation
of Certificates, Critique and Conclusion
11:45 to 12:15 P Return to motel
|
|
|
|
|
|
|
The VON Corporation, P.O. Box 110096, 1038 Lomb Avenue SW
Birmingham, AL 35211 (205)788-2437 |
|